[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892068":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892068,577,2,"多选题","依据《通用安装工程工程量计算规范》（GB 50856—2013），属于安全文明施工措施项目的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","环境保护",true,{"key":16,"text":17,"correct":14},"B","安全施工",{"key":19,"text":20,"correct":14},"C","临时设施",{"key":22,"text":23,"correct":24},"D","已完工程及设备保护",false,"ABC","本题考查的是安装工程措施项目清单。安全文明施工及其他措施项目中包括：安全文明施工（含环境保护、文明施工、安全施工、临时设施）、夜间施工增加、非夜间施工增加、二次搬运、冬雨季施工增加、已完工程及设备保护、高层施工增加。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]