[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892059":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892059,577,2,"多选题","《2017安装工程预算定额》的主要内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","文字说明",true,{"key":16,"text":17,"correct":14},"B","工程量计算规则",{"key":19,"text":20,"correct":21},"C","清单项目表",false,{"key":23,"text":24,"correct":21},"D","施工平面图",{"key":26,"text":27,"correct":14},"E","定额项目表","ABE","本题考查的是《安装工程预算定额》。《2017安装工程预算定额》的主要内容包括文字说明、工程量计算规则、定额项目表及附录。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]