[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892054":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892054,577,2,"多选题","编制分部分项工程量清单时，除了统一项目名称外，还必须符合的统一要求（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","统一项目编码",true,{"key":16,"text":17,"correct":14},"B","统一工程量计算规则",{"key":19,"text":20,"correct":21},"C","统一项目特征说明",false,{"key":23,"text":24,"correct":14},"D","统一计量单位","ABD","编制分部分项工程量清单时，必须符合四个统一的要求，即统一项目编码、统一项目名称、统一计量单位和统一工程量计算规则。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]