[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892053":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},892053,577,2,"多选题","依据《通用安装工程工程量计算规范》（GB 50856—2013）的规定，项目安装高度若超过基本高度时，应在项目特征中描述。各附录基本安装高度为6m的项目名称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","附录G通风空调工程",true,{"key":16,"text":17,"correct":18},"B","附录J消防工程",false,{"key":20,"text":21,"correct":18},"C","附录K给排水、采暖、燃气工程",{"key":23,"text":24,"correct":14},"D","附录M刷油、防腐蚀、绝热工程","AD","项目安装高度若超过基本高度时，应在“项目特征”中描述。《安装计量规范》安装工程各附录基本安装高度为：附录A机械设备安装工程10m，附录D电气设备安装工程5m，附录E建筑智能化工程5m，附录G通风空调工程6m，附录J消防工程5m，附录K 给排水、采暖、燃气工程3.6m，附录M刷油、防腐蚀、绝热工程6m。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]