[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892032":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892032,577,2,"多选题","卫生器具交工前应做（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","满水试验",true,{"key":16,"text":17,"correct":18},"B","严密性试验",false,{"key":20,"text":21,"correct":18},"C","灌水试验",{"key":23,"text":24,"correct":14},"D","通水试验",{"key":26,"text":27,"correct":18},"E","通球试验","AD","本题考查的是给排水、采暖、燃气工程施工技术。卫生器具交工前应做满水和通水试验。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]