[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891998":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},891998,577,2,"多选题","发生不可抗力事件后，应该由承包单位承担的损失有（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已运至施工现场的材料和工程设备的损坏",false,{"key":16,"text":17,"correct":18},"B","承包方的人员伤亡和财产的损失",true,{"key":20,"text":21,"correct":18},"C","承包人施工设备的损坏",{"key":23,"text":24,"correct":14},"D","承包人在停工期间按照发包人要求留在施工场地的必要的管理人员及保卫人员的费用","BC","",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]