[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891991":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},891991,577,2,"多选题","施工项目管理规划中（ ）的选择直接影响措施清单的编制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工方案",true,{"key":16,"text":17,"correct":14},"B","施工方法",{"key":19,"text":20,"correct":21},"C","施工现场管理",false,{"key":23,"text":24,"correct":21},"D","施工平面图","AB","施工措施项目的列项及其计量根据施工项目管理规划进行，施工项目管理规划主要内容有：施工方案和施工方法、施工现场管理和施工平面图等。施工方案和施工方法的选择直接影响措施清单编制",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]