[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891986":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},891986,577,2,"多选题","根据《建设工程工程量清单计价规范》（GB-50500-2013），关于分部分项工程量清单的编制，下列说法正确的有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以重量计算的项目，其计量单位应为吨或千克",true,{"key":16,"text":17,"correct":14},"B","以吨为计量单位时，其计算结果应保留三位小数",{"key":19,"text":20,"correct":21},"C","以立方米为计量单位时，其计算结果应保留三位小数",false,{"key":23,"text":24,"correct":21},"D","以千克为计量单位时，其计算结果应保留一位小数","AB","C选项，以立方米为计量单位时，其计算结果应保留二位小数。D选项，以千克为计量单位时，其计算结果应保留二位小数。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]