[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891985":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},891985,577,2,"多选题","安装工程工程量清单包括五部分，有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",true,{"key":16,"text":17,"correct":14},"B","措施项目清单",{"key":19,"text":20,"correct":21},"C","工程量计量规则",false,{"key":23,"text":24,"correct":14},"D","规费项目清单","ABD","安装工程工程量清单包括五部分，有分部分项工程量清单、措施项目清单、其他项目清单、规费项目清单和税金项目清单。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]