[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891868":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891868,577,2,"多选题","因承包人违约解除合同的，发包人应暂停向承包人支付任何价款。承包人违约导致合同解除的，应包括的费用有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","撤离现场及遣散人员的费用",false,{"key":16,"text":17,"correct":18},"B","已完成永久工程的价款",true,{"key":20,"text":21,"correct":18},"C","临时设施的摊销费用",{"key":23,"text":24,"correct":18},"D","签证、索赔以及其他应支付的费用",{"key":26,"text":27,"correct":18},"E","其他应由承包人承担的费用","BCDE","因承包人违约解除合同的，发包人应暂停向承包人支付任何价款。发包人应在合同解除后28天内核实合同解除时承包人已完成的全部合同价款以及按施工进度计划已运至现场的材料和工程设备货款，按合同约定核算承包人应支付的违约金以及造成损失的索赔金额，并将结果通知承包人。承包人违约导致合同解除的，应包括以下费用：①已完成永久工程的价款；②已付款的材料设备等物品的金额（付款后归发包人所有）；③临时设施的摊销费用；④签证、索赔以及其他应支付的费用；⑤承包人违约给发包人造成的实际损失（其违约责任的分担按委托人的决定执行）；⑥其他应由承包人承担的费用。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]