[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891867":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891867,577,2,"多选题","承包人向发包人提出工期索赔的依据包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同约定或双方认可的施工总进度规划",true,{"key":16,"text":17,"correct":14},"B","合同双方认可的详细进度计划",{"key":19,"text":20,"correct":21},"C","施工质量资料",false,{"key":23,"text":24,"correct":14},"D","合同双方认可的对工期的修改文件",{"key":26,"text":27,"correct":14},"E","影响工期的干扰事件","ABDE","承包人向发包人提出工期索赔的具体依据主要包括：①合同约定或双方认可的施工总进度规划；②合同双方认可的详细进度计划；③合同双方认可的对工期的修改文件；④施工日志、气象资料；⑤业主或工程师的变更指令；⑥影响工期的干扰事件；⑦受干扰后的实际工程进度等。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]