[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891865":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891865,577,2,"多选题","索赔费用的计算方法包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实际费用法",true,{"key":16,"text":17,"correct":18},"B","调值公式法",false,{"key":20,"text":21,"correct":14},"C","总费用法",{"key":23,"text":24,"correct":14},"D","修正的总费用法",{"key":26,"text":27,"correct":18},"E","比较法","ACD","索赔费用的计算应以赔偿实际损失为原则，包括直接损失和间接损失。索赔费用的计算方法通常有三种：①实际费用法。实际费用法又称分项法，即根据索赔事件所造成的损失或成本增加，按费用项目逐项进行分析、计算索赔金额的方法；②总费用法。总费用法，也被称为总成本法，就是当发生多次索赔事件后，重新计算工程的实际总费用，再从该实际总费用中减去投标报价时的估算总费用，即为索赔金额；③修正的总费用法。修正的总费用法是对总费用法的改进，即在总费用计算的原则上，去掉一些不合理的因素，使其更为合理。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]