[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891864":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891864,577,2,"多选题","工程变更的范围和内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","增加或减少合同中任何工作",true,{"key":16,"text":17,"correct":14},"B","改变合同中任何工作的质量标准",{"key":19,"text":20,"correct":21},"C","取消合同中的任何一项工作",false,{"key":23,"text":24,"correct":14},"D","改变工程的基线、标高、位置和尺寸",{"key":26,"text":27,"correct":14},"E","改变工程的时间安排或实施顺序","ABDE","根据《建设工程施工合同（示范文本）》（GF—2017—0201）的规定，工程变更的范围和内容包括：①增加或减少合同中任何工作，或追加额外的工作；②取消合同中任何工作，但转由他人实施的工作除外；③改变合同中任何工作的质量标准或其他特性；④改变工程的基线、标高、位置和尺寸；⑤改变工程的时间安排或实施顺序。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]