[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891854":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891854,577,2,"多选题","定额的消耗量指标一般包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","人工消耗量",true,{"key":16,"text":17,"correct":18},"B","建筑工程消耗量",false,{"key":20,"text":21,"correct":14},"C","材料消耗量",{"key":23,"text":24,"correct":14},"D","机械台班消耗量",{"key":26,"text":27,"correct":14},"E","预算定额基价","ACDE","定额的消耗量指标一般包括：①人工消耗定额。反映了完成某一分项工程的单位产品所耗用的各工种的工日数，可用综合工日表示，也可以按用工等级表示；②材料消耗定额。规定了完成某一分项工程的单位产品所耗用或摊销的各种主要材料、半成品、配件或周转材料的数量；③机械台班消耗定额。规定了完成某一分项工程的单位产品所耗用的各种施工机械台班的数量；④预算定额基价。一般都列有单位产品基价，它反映了某一分项工程单位产品的预算价格。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]