[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891853":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891853,577,2,"多选题","预算定额手册一般包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","机械台班消耗定额",false,{"key":16,"text":17,"correct":18},"B","文字说明",true,{"key":20,"text":21,"correct":18},"C","费用定额",{"key":23,"text":24,"correct":18},"D","工程量计算规则",{"key":26,"text":27,"correct":18},"E","定额项目表","BCDE","预算定额手册一般包括文字说明、工程量计算规则、定额项目表及有关附录等：①文字说明。文字说明包括总说明、册说明和各章说明；②工程量计算规则。消耗量定额中的工程量计算规则综合考虑了施工方法、施工工艺和施工质量要求，计算出的工程量一般要考虑施工中的余量，与定额项目的消耗量指标相互配套使用；③定额项目表。定额项目表是消耗量定额的核心内容，包括工作内容、定额编号、定额项目名称、定额计量单位及消耗量指标。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]