[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891828":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},891828,577,2,"多选题","依据《通用安装工程工程量计算规范》（GB 50856—2013），对于在工业管道主管上挖眼接管的三通，下列关于工程量计量表述正确的有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","三通不计管件制作工程量",true,{"key":16,"text":17,"correct":14},"B","三通支线管径小于主管径1\u002F2时，不计算管件安装工程量",{"key":19,"text":20,"correct":21},"C","三通以支管径计算管件安装工程量",false,{"key":23,"text":24,"correct":14},"D","三通以主管径计算管件安装工程量","ABD","依据《通用安装工程工程量计算规范》（GB 50856—2013），在主管上挖眼接管的三通和摔制异径管，均以主管径按管件安装工程量计算，不另计制作费和主材费；挖眼接管的三通支线管径小于主管径1\u002F2时，不计算管件安装工程量；在主管上挖眼接管的焊接接头、凸台等配件，按配件管径计算管件工程量。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]