[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891814":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},891814,577,2,"多选题","根据《安装工程计量规范》的规定，清单项目的五要素有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目名称",true,{"key":16,"text":17,"correct":14},"B","项目特征",{"key":19,"text":20,"correct":14},"C","计量单位",{"key":22,"text":23,"correct":24},"D","工程量计量规则",false,"ABC","",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]