[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891716":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891716,577,2,"多选题","环境管理计划的内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","根据项目施工预算，制订项目施工成本目标",false,{"key":16,"text":17,"correct":18},"B","确定项目重要环境因素，制订项目环境管理目标",true,{"key":20,"text":21,"correct":18},"C","建立项目环境管理的组织机构并明确职责",{"key":23,"text":24,"correct":18},"D","根据项目特点进行环境保护方面的资源配置",{"key":26,"text":27,"correct":18},"E","制订现场环境保护的控制措施","BCDE","环境管理计划可参照《环境管理体系要求及使用指南》（GB\u002FT 24001），在施工单位环境管理体系的框架内编制。环境管理计划应包括下列内容：①确定项目重要环境因素，制订项目环境管理目标；②建立项目环境管理的组织机构并明确职责；③根据项目特点进行环境保护方面的资源配置；④制订现场环境保护的控制措施；⑤建立现场环境检查制度，并就环境事故的处理做出相应的规定。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]