[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891715":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891715,577,2,"多选题","施工部署根据建设项目的性质、规模和客观条件的不同而有所不同，其具体表现有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","确定项目施工目标",true,{"key":16,"text":17,"correct":14},"B","确定项目分阶段（期）交付的计划",{"key":19,"text":20,"correct":21},"C","建立项目环境管理的组织机构并明确职责",false,{"key":23,"text":24,"correct":14},"D","确定项目分阶段（期）施工的合理顺序及空间组织",{"key":26,"text":27,"correct":14},"E","对主要分包项目施工单位的资质和能力提出明确要求","ABDE","施工部署根据建设项目的性质、规模和客观条件的不同而有所不同，具体表现如下：①确定项目施工目标，包括进度、质量、安全、环境和成本等目标；②根据项目施工总目标的要求，确定项目分阶段（期）交付的计划；③确定项目分阶段（期）施工的合理顺序及空间组织；④对项目施工的重点和难点就组织管理和施工技术两个方面进行简要分析；⑤总承包单位应明确项目管理组织机构形式，并确定项目经理部的工作岗位设置及其职责划分；⑥对开发和应用的新技术、新工艺、新材料和新设备做出部署；⑦对主要分包项目施工单位的资质和能力提出明确要求。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]