[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891713":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891713,577,2,"多选题","建设工程组织固定节拍流水施工的特点有( )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工过程在各施工段上的流水节拍不尽相等",false,{"key":16,"text":17,"correct":18},"B","各专业工作队在各施工段上能够连续作业",true,{"key":20,"text":21,"correct":18},"C","相邻施工过程之间的流水步距相等",{"key":23,"text":24,"correct":14},"D","专业工作队数大于施工过程数",{"key":26,"text":27,"correct":18},"E","各施工段之间没有空闲时间","BCE","",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]