[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891712":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891712,577,2,"多选题","加快的成倍节拍流水施工的特点有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","同一施工过程在各个施工段上的流水节拍均相等",true,{"key":16,"text":17,"correct":18},"B","相邻施工过程的流水步距等于流水节拍",false,{"key":20,"text":21,"correct":14},"C","各个专业工作队在施工段上能够连续作业",{"key":23,"text":24,"correct":18},"D","每个施工过程均成立一个专业工作队",{"key":26,"text":27,"correct":14},"E","所有施工段充分利用且没有空闲时间","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]