[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891711":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891711,577,2,"多选题","某工程双代号网络图如下图所示，绘图错误有 ( )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个起点节点",false,{"key":16,"text":17,"correct":18},"B","存在循环回路",true,{"key":20,"text":21,"correct":18},"C","节点编号有误",{"key":23,"text":24,"correct":18},"D","多个终点节点",{"key":26,"text":27,"correct":14},"E","有无箭头的连线","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]