[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891686":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},891686,577,2,"多选题","对于焊接连接的调节阀、节流阀等，管道吹扫时应采取的保护措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","与吹扫系统隔离",false,{"key":16,"text":17,"correct":18},"B","流经旁路",true,{"key":20,"text":21,"correct":18},"C","卸掉阀头及阀座",{"key":23,"text":24,"correct":14},"D","设置禁区",{"key":26,"text":27,"correct":14},"E","清洗干净相关工具","BC","管道吹扫与清洗前，应将系统内的仪表、孔板、节流阀、调节阀、电磁阀、安全阀、止回阀等管道组件暂时拆除，以模拟件或临时短管替代，待管道吹洗合格后再重新复位。对以焊接形式连接的上述阀门、仪表等部件，应采取流经旁路或卸掉阀头及阀座加保护套等保护措施后再进行吹扫与清洗。",{"id":6,"name":31,"category":32,"favorite":33},"[安装工程]建设工程计量与计价实务","建筑工程",0]