[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891661":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},891661,577,2,"多选题","管道进行水压试验时，试压前的准备工作包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安装临时注水和排水管线",true,{"key":16,"text":17,"correct":14},"B","管道系统的最高点安装排气阀",{"key":19,"text":20,"correct":14},"C","管道系统的末端安装排气阀",{"key":22,"text":23,"correct":24},"D","管道系统的最低点安装压力表",false,"ABC","管道水压试压前的准备工作包括：①安装试验用的临时注水和排水管线；②在试验管道系统的最高点和管道末端安装排气阀；③在管道的最低处安装排水阀；④压力表应安装在最高点，试验压力以此表为准。",{"id":6,"name":28,"category":29,"favorite":30},"[安装工程]建设工程计量与计价实务","建筑工程",0]