[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891581,577,1,"单选题","关于建筑设备自动化系统工程执行中应注意的问题，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制器安装未包括了单个控制器软件功能检测等工作内容",true,{"key":16,"text":17,"correct":18},"B","第三方通信设备接口中没有出的项目可执行其他接口子目",false,{"key":20,"text":21,"correct":18},"C","建筑设备自控化系统调试和系统试运行是以整个系统为单位进行编制的",{"key":23,"text":24,"correct":18},"D","建筑设备自动化系统试运行是在系统连续不间断运行120h条件下编制的","知识点:建筑智能化工程计量及应用案例。控制器安装包括了单个控制器软件功能检测等工作内容。参见教材P299。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]