[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891552":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891552,577,1,"单选题","根据2012电气设备安装工程预算定额，关于电缆敷设，错误的说法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不适用在积水区.水底.井下等特殊条件下的电缆敷设",false,{"key":16,"text":17,"correct":14},"B","定额是按平原地区施工条件编制的，如实际施工在丘陵.山地地带，其调整方法见架空线路的相应内容",{"key":19,"text":20,"correct":21},"C","电力电缆敷设定额均按三芯（包括三芯连地）编制，五芯和六芯电力电缆敷设定额乘以系数1.3",true,{"key":23,"text":24,"correct":14},"D","预制分支电缆敷设，每个分支的电缆长度定额是按10m以内编制的，若实际长度大于10m，超出部分安装费用另行计算","知识点:建筑电气工程定额应用。电力电缆敷设定额均按三芯（包括三芯连地）编制，五芯电力电缆敷设定额乘以系数1.3，六芯电力电缆乘以系数1.6，每增加一芯定额增加30%，单芯电力电缆敷设按同等截面电缆定额乘以系数0.67。参见教材P255。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]