[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},891551,577,1,"单选题","根据2012电气设备安装工程预算定额，下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","脚手架使用费按人工费的5%计算，其中人工费占25%",false,{"key":16,"text":17,"correct":18},"B","建筑物檐高按建筑物檐高40 m以下编制",true,{"key":20,"text":21,"correct":14},"C","超过25m的高层建筑，计算高层建筑增加费",{"key":23,"text":24,"correct":14},"D","建筑物檐髙以室外设计地坪标高作为计算起点","知识点:建筑电气工程定额应用。建筑物檐高按建筑物檐高25 m以下编制，超过25m的高层建筑，计算高层建筑增加费。参见教材P253。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]