[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891534":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891534,577,1,"单选题","消防工程执行定额中，管件、法兰数量应按设计图纸用量另行计算，螺栓按设计用量加（ ）%损耗计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","1",false,{"key":20,"text":21,"correct":18},"C","5",{"key":23,"text":24,"correct":18},"D","2","知识点:消防工程计量及应用。消防工程执行定额中注意，管件、法兰数量应按设计图纸用量另行计算，螺栓按设计用量加3%损耗计算。参见教材P215。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]