[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},891505,577,1,"单选题","制冷设备安装前，拆箱应（ ）顺序进行。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","从左到右",false,{"key":16,"text":17,"correct":14},"B","从前到后",{"key":19,"text":20,"correct":14},"C","自下而上",{"key":22,"text":23,"correct":24},"D","自上而下",true,"知识点:通风与空调工程施工技术。拆箱应自上而下顺序进行，拆箱时应注意保护机组的管路、仪表及电气、设备等不受损坏。参见教材P139。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]