[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891498":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},891498,577,1,"单选题","下列选项中，关于除锈工程说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设备.管道除锈以m2计量",false,{"key":16,"text":17,"correct":14},"B","钢结构除锈以kg计量",{"key":19,"text":20,"correct":14},"C","各种管件.阀件及设备上人孔.管口凹凸部分的除锈不再单独计算其除锈工程量",{"key":22,"text":23,"correct":24},"D","Sa2级或Sa1级，则人工.材料和机械乘以系数1.1",true,"知识点:《2012安装预算定额》第十二册《刷油、防腐蚀、绝热工程》。喷射除锈按Sa2.5级标准确定。若变更级别标准，如Sa3级，按人工、材料和机械乘以系数1.1；Sa2级或Sa1级，则人工、材料和机械乘以系数0.9。参见教材P115～116。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]