[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891463,577,1,"单选题","依据《通用安装工程工程量计算规范》（GB50856-2013），中压锅炉烟、风、煤管道安装应根据项目特征，按设计图示计算。其计量单位为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","t",true,{"key":16,"text":17,"correct":18},"B","m",false,{"key":20,"text":21,"correct":18},"C","m2",{"key":23,"text":24,"correct":18},"D","套","中压锅炉烟、风、煤管道安装。烟道、热风道、冷风道、制粉管道、送粉管道、原煤管道应根据项目特征（管道形状、管道断面尺寸、管壁厚度），以“t”为计量单位，按设计图示质量计算。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]