[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891462":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},891462,577,1,"单选题","下列关于最高投标限价编制应注意问题，说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","综合单价应考虑风险因素",false,{"key":16,"text":17,"correct":14},"B","定额综合单价中的企业管理费.利润应按现行定额费率及相关文件规定标准执行",{"key":19,"text":20,"correct":14},"C","税金.规费等法律.法规.规章和政策变化的风险不应纳入综合单价",{"key":22,"text":23,"correct":24},"D","人工单价风险费用纳入综合单价",true,"知识点:安装工程工程量清单计价。税金、规费等法律、法规、规章和政策变化的风险和人工单价等风险费用不应纳入综合单价。参见教材P55。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]