[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891458":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891458,577,1,"单选题","下列费用中，不包含在其他项目费中的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":14},"B","计日工",{"key":19,"text":20,"correct":21},"C","企业管理费",true,{"key":23,"text":24,"correct":14},"D","总承包服务费","知识点:安装工程工程量清单计价。其他项目费包括暂列金额、暂估价、计日工、总承包服务费。参见教材P55。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]