[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891456":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891456,577,1,"单选题","下列选项中，定额项目表不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算总价",true,{"key":16,"text":17,"correct":18},"B","工作内容",false,{"key":20,"text":21,"correct":18},"C","计量单位",{"key":23,"text":24,"correct":18},"D","人材机消耗量","知识点:安装工程预算定额。定额项目表是定额构成的核心内容，包括工作内容、定额编号、子目名称、计量单位、人材机消耗量及预算单价。参见教材P46。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]