[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891454":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891454,577,1,"单选题","汇总工程量时，下列精度取值不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以“t”为单位，应保留三位小数",false,{"key":16,"text":17,"correct":14},"B","以“台”.“套”或“件”等为单位，应取整数",{"key":19,"text":20,"correct":21},"C","以“台”.“套”或“件”等为单位，应保留四位小数",true,{"key":23,"text":24,"correct":14},"D","以“m3”.“m2”.“m”为单位，应保留两位小数","知识点:安装工程分部分项工程工程量清单。其精度取值：以“m3”、“m2”、“m”为单位，应保留两位小数；以“t”为单位，应保留三位小数；以“台”、“套”或“件”等为单位，应取整数，两位或三位小数后的位数应按四舍五入法取舍。参见教材P39。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]