[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891447,577,1,"单选题","《安全文明施工及其他措施项目一览表》中的措施项目一般不能计算工程量，以（ ）为计量单位计量。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","个",false,{"key":16,"text":17,"correct":14},"B","次",{"key":19,"text":20,"correct":21},"C","项",true,{"key":23,"text":24,"correct":14},"D","条","知识点:安装工程措施项目清单。《安全文明施工及其他措施项目一览表》中的措施项目一般不能计算工程量，以“项”为计量单位计量。参见教材P40。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]