[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891402":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},891402,577,1,"单选题","施工组织设计技术经济分析步骤的正确顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工方案技术经济分析—施工平面图分析—施工进度分析—综合技术经济分析—决策",false,{"key":16,"text":17,"correct":18},"B","施工方案技术经济分析—施工进度分析—施工平面图分析—综合技术经济分析—决策",true,{"key":20,"text":21,"correct":14},"C","施工方案技术经济分析—综合技术经济分析—施工进度分析—施工平面图分析—决策",{"key":23,"text":24,"correct":14},"D","施工方案技术经济分析—施工进度分析—综合技术经济分析—施工平面图分析—决策","知识点:施工组织设计技术经济分析。施工组织设计技术经济分析的步骤为：施工方案技术经济分析—施工进度分析—施工平面图分析—综合技术经济分析—决策。参见教材P31。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]