[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891401":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891401,577,1,"单选题","施工总平面图布置图的一般设计步骤包括了：①起重机的位置②设备组合加工及堆放场地③供水、供电、供热线路④交通运输⑤计算经济指标⑥办公、生活临时设施⑦设备、材料、机械库区⑧修改审批⑨综合对比评价。其中顺序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②⑦④⑥③⑤⑨⑧",true,{"key":16,"text":17,"correct":18},"B","①②④⑥⑦③⑤⑨⑧",false,{"key":20,"text":21,"correct":18},"C","①②⑤⑦④⑥③⑨⑧",{"key":23,"text":24,"correct":18},"D","①②⑦④⑤⑥③⑨⑧","知识点:施工总平面图设计。施工总平面布置图的设计步骤一般是：起重机的位置—设备组合加工及堆放场地—设备、材料、机械库区—交通运输—办公、生活临时设施—供水、供电、供热线路—计算经济指标—综合对比评价—修改―审批。参见教材P31。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]