[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891400,577,1,"单选题","下列关于施工组织设计编制内容的描述中，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","主要技术经济指标包括人力.工期.机械设备的利用程度.项目成本等",false,{"key":16,"text":17,"correct":14},"B","人力资源计划宜包括高峰人数.月平均人数.逐月累计人工数及总人工时等",{"key":19,"text":20,"correct":21},"C","施工总进度计划图表通常用垂直图或网络图表述",true,{"key":23,"text":24,"correct":14},"D","程概况用于介绍建设项目的基本情况.设计概况和现场条件等","知识点:施工组织设计。C错误，施工总进度计划图表通常用横道图或网络图表述。参见教材P28。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]