[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891339":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891339,577,1,"单选题","大中型企业由于负荷较大，往往采用35kV（或以上）电源进线，降压至10kV或6kV，再向各车间变电所和高压用电设备配电，称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总降压变电所",true,{"key":16,"text":17,"correct":18},"B","车间变电所",false,{"key":20,"text":21,"correct":18},"C","独立变电所",{"key":23,"text":24,"correct":18},"D","杆上变电所","本题考查的是建筑电气工程施工技术。总降压变电所。大中型企业由于负荷较大，往往采用35kV（或以上）电源进线，降压至10kV或6kV，再向各车间变电所和高压用电设备配电，称为总降压变电所。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]