[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891305":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891305,577,1,"单选题","排出管在隐蔽前必须做（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","水压试验",false,{"key":16,"text":17,"correct":14},"B","通球试验",{"key":19,"text":20,"correct":21},"C","灌水试验",true,{"key":23,"text":24,"correct":14},"D","通水试验","本题考查的是给排水、采暖、燃气工程施工技术。排出管在隐蔽前必须做灌水试验。排水立管应作通球试验。排水横支管、立管应做灌水试验。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]