[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},891295,577,1,"单选题","工程变更引起分部分项工程项目发生变化时，采用已标价工程量清单中有适用于变更工程项目的单价，则该工程数量变化不足（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3%",false,{"key":16,"text":17,"correct":14},"B","5%",{"key":19,"text":20,"correct":14},"C","10%",{"key":22,"text":23,"correct":24},"D","15%",true,"本题考查的是安装工程工程量清单计价。工程变更引起分部分项工程项目发生变化时，应按照下列规定调整：已标价工程量清单中有适用于变更工程项目的，工程数量变化不足15%时，采用该项目的单价。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]