[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891292,577,1,"单选题","某电气工程在楼板内敷设JDG薄壁钢管DN25，工程量为1.0m，预算定额表中人工综合0.08工日，定额人工单价114.89元\u002F工日（市场价格为130元\u002F工日），材料费1.53元\u002Fm，JDG薄壁钢管为1.03m（施工期市场价为3元\u002Fm），管理费和利润为3.21元\u002Fm，则该分项工程综合单价为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","13.81元",false,{"key":16,"text":17,"correct":14},"B","13.93元",{"key":19,"text":20,"correct":21},"C","17.02元",true,{"key":23,"text":24,"correct":14},"D","18.23元","本题考查的是安装工程预算定额。综合单价＝人工费+（材料费+主材费）+机械台班费+管理费和利润＝0.08×114.89+（1.53+1.03×3）+0+3.21＝9.1912+4.62+3.21＝17.02元",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]