[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891291":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},891291,577,1,"单选题","《2017安装预算定额》中某项未计价材料费（主材费）计算为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","某项未计价材料数量×材料预算单价",false,{"key":16,"text":17,"correct":14},"B","某项未计价材料数量×材料采购价格",{"key":19,"text":20,"correct":14},"C","某项未计价材料数量×材料不含税（增值税）价格",{"key":22,"text":23,"correct":24},"D","某项未计价材料数量×材料市场价格",true,"本题考查的是安装工程预算定额。某项未计价材料费（主材费）＝某项未计价材料数量×市场价格。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]