[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},891287,577,1,"单选题","在编制工业管道预制安装时，措施项目清单可列项的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","防冻防雨措施",false,{"key":16,"text":17,"correct":14},"B","焊缝真空检验",{"key":19,"text":20,"correct":14},"C","焊接保护措施",{"key":22,"text":23,"correct":24},"D","平台铺设、拆除",true,"本题考查的是安装工程措施项目清单。当拟建工程中有工艺钢结构预制安装和工业管道预制安装时，措施项目清单可列项“平台铺设、拆除“。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]