[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891282":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},891282,577,1,"单选题","施工组织设计技术经济分析步骤为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工进度分析—施工方案技术经济分析—施工平面图分析—综合技术经济分析—决策",false,{"key":16,"text":17,"correct":14},"B","施工方案技术经济分析—施工平面图分析—施工进度分析—综合技术经济分析—决策",{"key":19,"text":20,"correct":14},"C","施工平面图分析—施工进度分析—施工方案技术经济分析—综合技术经济分析—决策",{"key":22,"text":23,"correct":24},"D","施工方案技术经济分析—施工进度分析—施工平面图分析—综合技术经济分析—决策",true,"本题考查的是施工组织设计技术经济分析。施工组织设计技术经济分析步骤为：施工方案技术经济分析—施工进度分析—施工平面图分析—综合技术经济分析—决策。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]