[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891250":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891250,577,1,"单选题","下列关于工程变更的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安全文明施工费，按照实际发生变化的措施项目调整，不得浮动",false,{"key":16,"text":17,"correct":14},"B","采用单价计算的措施项目费，按照实际发生变化的措施项目按分部分项工程费的调整方法确定单价",{"key":19,"text":20,"correct":21},"C","按总价计算的措施项目费，按照实际发生变化的措施项目调整，考虑承包人报价浮动因素",true,{"key":23,"text":24,"correct":14},"D","发包人提出的工程变更，非因承包人原因删减了合同中的某项原定工作或工程，承包人有权提出并得到合理的费用及利润补偿","本题考查的是安装工程工程量清单计价。选项C错误，按总价（或系数）计算的措施项目费，除安全文明施工费外，按照实际发生变化的措施项目调整，但应考虑承包人报价浮动因素，即调整金额按照实际调整金额乘以按照承包人报价浮动率计算。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]