[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891248":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891248,577,1,"单选题","分部分项工程中，已标价工程量清单中有适用于变更工程项目的，且工程变更导致的该清单项目的工程数量变化不足（ ）时，采用该项目的单价。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10%",false,{"key":16,"text":17,"correct":14},"B","12%",{"key":19,"text":20,"correct":21},"C","15%",true,{"key":23,"text":24,"correct":14},"D","20%","本题考查的是安装工程工程量清单计价。巳标价工程量清单中有适用于变更工程项目的，且工程变更导致的该清单项目的工程数量变化不足15%时，采用该项目的单价。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]