[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891243,577,1,"单选题","根据土建工程定额综合单价计算程序，企业管理费的计算基数是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工费+材料费+机械费",true,{"key":16,"text":17,"correct":18},"B","人工费+材料（设备）费",false,{"key":20,"text":21,"correct":18},"C","材料（设备）费+机械费",{"key":23,"text":24,"correct":18},"D","人工费","本题考查的是安装工程工程量清单计价。根据土建工程定额综合单价计算程序，企业管理费的计算基数是人工费+材料费+机械费。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]