[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891238":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891238,577,1,"单选题","当拟建工程有重量大于40t的设备安装时，其专业工程措施项目清单可列项（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","金属抱杆安装拆除",true,{"key":16,"text":17,"correct":18},"B","平台铺设.拆除",false,{"key":20,"text":21,"correct":18},"C","现场施工围栏",{"key":23,"text":24,"correct":18},"D","二次搬运","本题考查的是安装工程措施项目清单。当拟建工程有重量大于40t的设备安装时，其专业工程措施项目清单可列项“金属抱杆安装拆除、移位”。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]